Solstice Travel: Two Projects, One Budget

Finance
medium40 min0 submissions
Razorpay
Scenario

Solstice Travel, a online travel company in Southeast Asia, has two capital projects competing for approval and only $223 M of approved capital this year.

Project A — Automation upgrade. Requires $116 M upfront and is expected to generate $37 M of incremental after-tax cash flow per year for 6 years.

Project B — New production line. Requires $255 M upfront and is expected to generate $110 M per year for 6 years.

The company's hurdle rate is 14%.

Two complications. First, the finance team has already spent $15 M on engineering studies for Project B, and the COO argues this money "shouldn't be wasted". Second, Project B's cash flows depend on a customer contract that is signed but renews annually.

Supporting data

project a

life years
6
investment m
116
annual cash flow m
37

project b

life years
6
investment m
255
annual cash flow m
110

constraints

hurdle rate pct
14
capital budget m
223
already spent on b studies m
15
Your task

Recommend how to allocate the capital budget. Provide:

  1. Analysis — NPV, IRR and payback for each project.
  2. Risks — including how you treat the engineering spend and the contract renewal risk.
  3. Recommendation — which project (or projects) to fund.
Ready to move forward? Up next: Halcyon Bank: Can We Raise Prices 16%?Next question
How you'll be graded

100 points, 60% to pass.

  • assumptions20
  • recommendation30
  • risk assessment20
  • financial analysis30
Hint
Reveal suggested structure
  1. NPV of each project using the annuity form: NPV = CF × [(1 − (1+r)^−n) ÷ r] − I₀
  2. IRR — the rate at which NPV = 0. Note that IRR alone misranks projects of different scale.
  3. Payback as a liquidity check, not a decision rule.
  4. Sunk cost — the $15 M is spent and irrecoverable. It must not enter the decision.
  5. Profitability index (NPV ÷ investment) when capital is rationed.
  6. Risk-adjust Project B for the annual renewal.