Tessellate: Orders Are Piling Up

Operations
easy35 min0 submissions
McKinsey
Scenario

Tessellate is a developer tools operation in US. Demand is 2,269 units per day and rising, but the site is not shipping it. Work-in-progress is accumulating and the plant manager is asking for capital.

The line has four stages, each with its own maximum rate:

StageCapacity
Intake1,698 units/day
Processing784 units/day
Quality check1,428 units/day
Dispatch1,856 units/day

Other facts:

  • The plant manager has requested $3 M to upgrade the Dispatch stage, because that is where the visible backlog sits
  • Each additional unit shipped contributes $244
  • Overtime is available at any stage, at a premium

The site director wants to know whether to approve the request.

Supporting data

proposal

cost
3
stage
Dispatch

economics

contribution per unit
244

derived hints

bottleneck stage
Processing
system throughput
784
unmet demand per day
1485
demand units per day2269

stage capacity units per day

intake
1698
dispatch
1856
processing
784
quality check
1428
Your task

Advise the site director. Your answer should provide:

  1. Analysis — what the site's actual throughput is and where the constraint sits, computed.
  2. Risks — what your answer depends on.
  3. Recommendation — where to spend, and the throughput it should buy.

State any assumptions you make.

Ready to move forward? Up next: Lumen Learning: Orders Are Piling UpNext question
How you'll be graded

100 points, 60% to pass.

  • root cause25
  • recommendation20
  • problem structuring25
  • quantitative analysis30
Hint
Reveal suggested structure

Stage capacities; theory of constraints; value of relieving the bottleneck; re-check the next constraint